Town of Dedham : Public Safety Building - What's Happening September 12, 2022 to September 16, 2022

From: Town Of Dedham
September 12, 2022

Here is a look-ahead at the construction work planned for the Public Safety Building, from September 12, 2022 to September 16, 2022

Project Overview:  

Construction of a combined public safety building commenced in December 2020 on the site of the former Town Hall at 26 Bryant Street. The new building will house the staff and equipment of Fire, Police, and Dispatch departments. The new combined Public Safety Building will replace two older Town buildings: Police Station at 600 High Street (built in 1962) and the Fire Station at 436 Washington Street (built in 1930). The new building is scheduled to open in the Fall of 2022.

A livestream video of the construction is available on the Project website! Tune in from anywhere to watch the continued progress on the Combined Public Safety Building. While there, check out the updated Before-and-After photos of the progress onsite.

What to expect September 12, 2022 (Monday) through September 16, 2022 (Friday):

-The project site remains closed to the public.
-Weekend work: Crews will continue working on the Bryant Street curb and install curbing behind Town Hall. Other work will include taping, sanding, finishes, and framing the metal cap at the North elevation.
-HVAC contractors will continue to install valves and piping for the induction units located on the second floor of the Police Station and basement. They will also work on insulating the induction unit piping on the second floor of the Fire Station.
-Sheet Metal contractors will work on induction units in the basement.
-The fire protection and sprinkler subcontractor will perform T&M work in the men’s locker room, complete wiring for the pre-action system in Dispatch, and flush the underground sprinkler piping.
-Plumbing will install finishes on the second floor of the Fire Station.
-Electrical contractors will install fire alarms, lighting, and electrical finishes in the basement. They will also install exterior lighting on the South elevation.
-Work will continue on the interior cold formed metal framing, dense glass taping and sanding in the basement, as well as other miscellaneous areas throughout the Public Safety Building.
-Painters will paint the mezzanine railings.
-Work will be done on grinding and parging walls in stairs #1 and #2 and installing a vapor barrier in the garage ramp.
-The Site Contractor will install light pole bases on Bryant Street.
-Work will continue on the installation of ceramic tile on the second floor of the Police and Fire Stations.
-The ACT ceiling installer will finish miscellaneous projects throughout the building.
-Millwork will install windowsills on the first and second floors of the Police Station.
-N.E. Decks & Floors will prepare the East side of the Apparatus Bay for epoxy flooring.
-Permanent Power was supplied to the building on July 28, 2022. The generator is due to arrive at the end of September.

Public Viewing Area:

If you want to stop by to check out the progress, stand by the picnic table outside the north entrance to Town Hall. This spot provides a great view into the project site and is outside of the project boundaries. Worth a visit!

Construction Hours:

Crews will be onsite:

-Saturday, September 10, 2022: 8:00 AM to 4:00 PM
-Monday through Friday: 7:00 AM to 5:00 PM

Project Team Contact Information:

-Immediate issues or concerns, please contact the Town Manager’s Office at 781-751-9100.
-For general questions or concerns, please contact the project team at psb@dedham-ma.gov
-For more information about the Public Safety Building Project, please visit the project website at www.dedham-ma.gov/psb
-Download our project team contact information flyer on the project website.